11 September 2012

Closing Ten Days Later



Final Product



Shower that caused the closing date to be delayed 10 days.  Minimum required entry is 22 inches.


Replaced with frameless glass and shaved inches off the left wall

23 August 2012

One More Week Until Closing



Front yard before


After.  The window shutters and blinds are in.



Courtyard


Backyard before


After


Back splash.  There is a crack on the counter top.  They may have to replace.  Final inspection has been scheduled for early next week.

13 August 2012

Week Seventeen Front Door Light Fixtures


The front minus landscape, gutters, and shutters


Half of the counter tops have arrived


New front door


Air conditioner

07 August 2012

Week Sixteen Three Bed Two and One Half Bath


The driveway and sidewalk are done.  The bathroom sinks and doorknobs are in.  There is still a lot of work to be done in the next three weeks including kitchen counter top and sink, fixing island, back splash, carpet, sprinklers and landscaping, gutters, and electrical work.

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight
Week Nine
Week Eleven
Week Twelve 

31 July 2012

Week Fifteen Tile

Driveway and sidewalk have been cleared



Cabinets.  The island on the right needs to be rotated.


Bathroom tile

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight
Week Nine
Week Eleven
Week Twelve 

23 July 2012

Week Fourteen Paint and Cabinets


Paint truck.  I could not take pictures inside because they were painting but will have pictures of the wall colors and cabinets next week.


Garage eyebrow brick trim done

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight
Week Nine
Week Eleven
Week Twelve

16 July 2012

Week Thirteen Doors, Baseboards, and Crown Molding




Brick trim above garage has not been completed



Back of house


09 July 2012

Week Twelve Drywall and Masonry

 

Masonry close to completion.  Garage door installed.

 

Kitchen drywall



Great room drywall

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight
Week Nine
Week Eleven

02 July 2012

Week Eleven Insulation and Masonry


Insulation and masonry in-progress.  Drywall should be completed this week.


Back of house and patio


Spray foam insulation

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight
Week Nine

15 June 2012

Week Nine Electrical and Alarm Prewire

Week 9

Not much change on the exterior besides the pile of dirt and the stack of drywall in the garage.  Pre-drywall inspection is scheduled for next Friday.

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five
Week Seven
Week Eight

Week Eight Roofing

13 June 2012

Week Seven Framing

Week 7

There is no picture for Week Six since I was out of town but you would seen the framing without the exterior drywall

Related Posts

New Home Construction
Week One
Week Two
Week Three
Week Four
Week Five